rayte

Spain · solar design

West-facing panels trade some noon output for later electricity.

The best orientation is not always the one with the largest annual kWh estimate. The useful question is when the home consumes electricity and what exported energy is worth.

1. Start with the household load curve

Record electricity use by hour before choosing an orientation. A home that is quiet at noon but busy from late afternoon may use a greater share of west-facing production directly. Pool pumps, cooling, cooking, water heating and vehicle charging can materially change the result.

Annual production remains important, but each kWh does not necessarily have the same financial value. A directly consumed kWh may avoid an import charge; an exported kWh receives the contract’s surplus value and may face a billing-period limit.

2. Compare orientations with the same assumptions

Use the European Commission’s PVGIS tool with the same location, installed kWp, mounting type and system-loss assumption. Change only the azimuth and slope. Compare annual output, monthly output and hourly profiles rather than quoting one headline percentage from a sales proposal.

3. Check the roof, shading and string design

A west roof can be strong in summer but shaded by terrain, chimneys or buildings in winter. Ask for a shade study and confirm that panels with materially different orientations are assigned to suitable MPPT inputs or separate inverters. String voltage, current, optimiser compatibility and inverter limits belong with the qualified designer and installer.

4. Model the value, not just the kWh

Comparison structure

Keep generation and financial value separate

Annual generation
PVGIS estimate by orientation
Direct use
Hourly overlap with household load
Export
Remaining eligible surplus
Value
Avoided import + export credit

Use current contract prices and test more than one future tariff. Do not assume the present import/export spread lasts for the system lifetime.

5. Consider clipping and existing equipment

Adding panels can improve inverter utilisation in shoulder hours while increasing clipping around peak production. Clipping is not automatically a design fault; its annual energy cost should be compared with the cost of larger equipment. Confirm thermal limits, warranty conditions, grid-connection constraints and whether the existing battery can accept the intended charging power.

6. Measure the extension as a separate change

  • Record the commissioning date and installed specification.
  • Preserve a complete pre-change year where possible.
  • Compare matching months and account for weather differences.
  • Track hourly production, import, export and battery flows.
  • Wait for a complete post-change year before presenting annual uplift.

A before-and-after comparison across unmatched seasons is not enough. May-to-August after an extension cannot be compared with a full prior calendar year without adjustment.

Rayte’s practical rule: value the timing of generation, but do not call a partial-year observation an annual result.

Official and related sources

Published 3 October 2026. Design and electrical work require a qualified professional and current local approvals.